A large steel water tank being inspected with a drone

Steel water tank drone inspection

A steel 500,000 litre above ground water tank needed inspecting and we knew just how to do it.
Overview

The Job at a Glance

Full internal and external drone inspection of a 500,000-litre above-ground galvanised steel fire suppression tank — completed in a single day, with no scaffolding, no confined space entry, and no extended shutdown.

500,000L galvanised steel tank

Above-ground fire suppression tank beside a busy warehouse, near a motorway and airport — full airspace and ground risk assessment completed before mobilisation.

1 day vs 1 month

Complete internal and external inspection returned the tank to service the same day, compared to an estimated month-long scaffolded shutdown.

No confined space entry

The drone flew in through the top access hatch — no personnel entered the tank at any point during the inspection.

Full condition report

PDF inspection report with damage classification, annotated imagery of all findings, and a summary of all severe defects.

Overview

Verify the integrity of a large above ground water tank

The client had a requirement to verify the integrity of a large above ground water tank they had on their property. The tank was primally used for storing water for fire suppression in the clients warehouse and so was an important piece of infrastructure. The client needed the tank inspected quickly in order to minimise downtime. They approached us to see what we could do for them.

Comparative methodology

Why they chose us

The client needed a 500,000-litre fire suppression tank inspected quickly and returned to service. A confined space drone completed the full internal and external assessment in a single day — with no scaffolding, no confined space entry, and no month-long shutdown.

Shutdown time
1 day vs 1 month

The tank was inspected and returned to service the same day, minimising disruption to the fire suppression system.

Time to complete
2 hours vs days of scaffolding

From drone entry to complete coverage of the interior walls, roof structure, and floor took under two hours.

Confined entry
Zero entry vs full permits required

No personnel entered the tank. The drone flew in through the top hatch with no confined space permits needed.

Efficient option Our method

Using a drone

This is what the job looked like using drone technology.

  • Shut down for 1 day only The tank was returned to service the same day, minimising disruption to the fire suppression system.
  • Inspection complete in 2 hours Internal walls, roof structure, and floor were all covered systematically using the drone's wall-lock function.
  • No confined space entry The drone entered through the top hatch. No personnel needed to enter the tank at any point.
  • Internal and external coverage The confined space drone covered the interior while the DJI Mavic 2 Zoom was used for external surfaces and fittings.
  • All penetrations documented Every wall, roof, and floor penetration was inspected and verified against a pre-prepared map to ensure full coverage.
  • Full condition report delivered A PDF report with damage classifications and annotated imagery of all findings was delivered to the client.
Tank status Back in service same day
Manned approach Traditional method

Without a drone

What the job would have looked like without drone technology.

  • Shut down for a month Traditional scaffolded inspection would have required the tank out of service for approximately a month.
  • Two tonnes of scaffolding All scaffold components would need to be assembled and disassembled inside the tank, brought in piece by piece through a 40cm access hatch.
  • Confined-space and height permits Every person inside the tank would require confined-space entry permits, working-at-height permits, and all supporting safety documentation.
Operational impact Month-long shutdown
Background

The Spec

Traditionally, the inspection of the water tank is done by a team of workers who use scaffolding to access the top of the tank. This method is time-consuming, expensive, and potentially dangerous. In addition, the scaffolding can cause damage to the tank's coating, which can lead to rust and other problems. Thus, the use of a confined space drone was proposed as an alternative method for inspecting the water tank.

The galvanised steel tank was large with a 500,000 litre capacity and was designed for holding water. It was located above ground next to a large warehouse. The site was also close to a busy motorway and airport. This made for some interesting challenges in the planning stage of this job.

The client required both the inside and outside of the tank to be inspected. They also requested a full conditional report on the tank with a clear damage classification system applied to all findings. A summary of the severe damages found and and imagery of all damages was also to be included.

Asset

About the tank

500,000-litre capacity

The inspected tank stores up to 500,000 litres of water for fire suppression.

Wall material

Galvanised steel wall construction across the tank shell.

Roof material

Corrugated metal roof structure.

Methodology

On-site inspection workflow

Before setting foot on site we performed a full assessment of the air risk and ground risk associated with this

On first getting to the tank we mapped all the visible designed penetrations in the walls, roof and floor. This map would be used to check off the same penetrations on the inside of the tank to ensure all of them were inspected. The tank had a hinged man access hatch at the top and a bolted man access hatch at ground level. We decided in order to minimise downtime that the top hatch would be the best way to get the drone into the tank. We liaised with the client representative on site to see if there were any specific items they wanted to look at before commencing work.

A severely corroded valve found on a confined space tank inspection
A severely corroded valve found on a confined space tank inspection

Once the ingress point was established we were able to fly the drone into the tank without issue. We started from the top and worked our way down. We complete an inspection of the roof structure, then the internal walls and finally the floor. Once this was complete we gathered detailed shots of all penetrations to have on record. There was still about four centimetres of water in the tank so we had to be careful not to get too close. Thankfully with so little water we could easily see though it and make an assessment of the condition of the floor. We used the "wall lock" function of the drone to stay a specific distance from the wall and inspected the tank in ever defending circles until the entire tank was covered.

For the external part of the tank we used hte small but powerful DJI Mavic 2 Zoom. THe zoom lens on this drone allowed us to get good high-resolution detailed photography of the external aspects of the tank without having to fly the drone dangerously close to the asset. We also used a digital SLR camera to capture elements close to the ground.

A standard procedure for us is to capture all the internal and external sides of every tank penetration no matter what it's condition. This is because we believe it is important for your clients to be able to verify our work. If we were to only show the defect then the client would not be able to verify that what we have given them was the complete extent of defect on the tank.

All active components of the tank were also checked. This includes items like valves, level sensors and any internal electrical infrastructure. A good example of this is the main outflow point as seen int he image above. The tank penetration appears to be in good shape and the pipe is not blocked or corroded ina ny way. Good for many more years of service.

It is important to see beyond he obvious defects when inspecting an asset like a tank. In the image below you can see the water has been consistently rising above the level of tanks roof structural elements. This is because the automatic shut off for the fill valves was seized solid and the water only stopped when it poured out the overflow port at the top of th tank. This was leading to wasted water and also . the

Water tank internal roof structure with roof members contaminated from water immersion
Water tank internal roof structure with roof members contaminated from water immersion

The client wanted a complete tank inspection and reporting including the external surfaces and fittings. Here we found the main supply hose had only two bolts keeping the flanged joint together. It did not appear to be leaking but it was only a matter of time before it did. It was "low hanging fruit" to fix so we were sure to include it in the report.

A flanged pipe joint with two of the securing bolts missing.
A flanged pipe joint with two of the securing bolts missing.

Deliverables

Full condition report

A PDF inspection report with a clear damage classification system, annotated imagery of all findings, and a summary of severe defects.

Outcome

A cost-effective, efficient and safe asset inspection

The use of a confined space drone for the inspection of the above ground galvanised steel water tank proved to be an effective, efficient, and safe method. The drone was able to capture high-resolution images and videos of the tank's exterior and interior, which allowed the inspector to identify any visible damage, corrosion, or structural issues. The use of the drone also saved time and reduced the risk to workers, which is crucial in confined space inspections. The success of this case study demonstrates the potential of drones in confined space inspections, and their ability to improve safety, efficiency, and accuracy in various industries.

Missing Bolt on tank inspection
Pipe improperly secured on side of water tank
Leaking plastric drain pipe
Roof level pipe penetration
Tank roof beam joint detail
External tank roof detail
Tank level gauge sensor port
Slime on inside wall of tank
Tank roof beam to wall interface detail
Let's talk

Speak to an engineer about your project

Complex surveys and inspections require more than just a pilot. Our engineers can help you scope your requirements and indentify the right approach.

Talk to an engineer

+353 (0)21 202 8281

Quickest for technical scoping

Email your brief

info@engineerswithdrones.ie

Best for sending detailed specs

Next steps

Where to find out more

Find out more about our confined space drone services and our tank and silo inspection services. Alternatively, you can contact us here to ask what we can do for you.

Last Updated: